goingcritical:akkuyu-1Türkiye · Power reactor

Akkuyu-1

Status: Under construction target criticality 2026 (confidence: medium) Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. Operating In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.

Site: Gülnar, Mersin Province

IsraelAzerbaijanAlbaniaIstanbulBaghdadHaifaGaziantepHimsIzmirMosul
Gülnar, Mersin Province36.1444° N, 33.5411° E
Summary:

First nuclear power reactor in Türkiye

Rosatom CEO (June 2026) - fuel loading and physical start-up scheduled for autumn 2026, following hot functional tests starting July 2026; dummy fuel loading completed June 2026

Details

DesignVVER-1200/V-509
Electrical output1,114 MWe

Milestone history

  1. Announced
  2. Construction start April 3, 2018
  3. Fuel load
  4. First criticality target 2026
  5. Grid connection
  6. Commercial operation