goingcritical:barakah-1United Arab Emirates · Power reactor
Barakah-1
Status: Operating critical since July 31, 2020 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.
Site: Barakah, Al Dhafra Region, Abu Dhabi
First nuclear power reactor in the Arab world
Details
| Design | APR-1400 (Generation III PWR) |
| Electrical output | 1,345 MWe |
Milestone history
- Announced —
- Construction start July 18, 2012
- Fuel load February 2020
- First criticality July 31, 2020
- Grid connection August 19, 2020
- Commercial operation April 1, 2021