goingcritical:borsseleNetherlands · Power reactor
Borssele
Status: Operating critical since June 20, 1973 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.
Site: Borssele, Zeeland
The Netherlands' only operating nuclear power reactor. A German KWU PWR that has been repeatedly life-extended and is central to Dutch plans for new nuclear build.
Details
| Design | Siemens/KWU 2-loop PWR |
| Electrical output | 482 MWe |
Milestone history
- Announced —
- Construction start July 1, 1969
- Fuel load —
- First criticality June 20, 1973
- Grid connection July 4, 1973
- Commercial operation October 26, 1973