Chinon A3 / EDF-3
Status: Shut down reached first criticality March 1, 1966 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.
Site: Chinon, Indre-et-Loire
Third and largest UNGG gas-graphite reactor at Chinon on the Loire. First went critical on 1 March 1966. Permanently shut down 15 June 1990.
Details
| Design | UNGG (gas-graphite, natural-uranium graphite-moderated, CO2-cooled) |
| Electrical output | 480 MWe |
Milestone history
- Announced —
- Construction start March 1, 1961
- Fuel load —
- First criticality March 1, 1966
- Grid connection August 4, 1966
- Commercial operation —