goingcritical:darlington-bwrx-300-1Canada · SMR
Darlington New Nuclear Project Unit 1 (BWRX-300)
Status: Under construction target criticality 2030 (confidence: medium) Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.
Site: Darlington New Nuclear Project site, Clarington, Ontario
First grid-scale SMR under construction in North America; CNSC issued the licence to construct Apr 4, 2025, and the first module (basemat) was placed May 1, 2026
OPG targets construction complete by end of 2029 and commercial operation by end of 2030 (criticality target not separately stated); operating licence application filed March 2026
Details
| Design | GE Vernova Hitachi BWRX-300 |
| Electrical output | 300 MWe |
Milestone history
- Announced —
- Construction start May 2025
- Fuel load —
- First criticality target 2030
- Grid connection —
- Commercial operation —
References
- CNSC, Apr 4 2025 — licence to construct one BWRX-300 at DNNP
- POWER, May 2025 — Ontario approves construction start (May 8, 2025); completion end-2029, in service end-2030
- Nuclear Engineering International, 2026 — first module (basemat) set in place May 1, 2026
- WNN, Mar 2026 — OPG applies for 20-year operating licence