goingcritical:palisadesUnited States · Restart
Palisades
Site: Covert Township, Michigan
Status: Under construction — target criticality 2026 (confidence: low) target
Summary:
First-ever US restart of a reactor from decommissioning status (shut down May 2022); NRC returned the plant to an operating license in 2025
Holtec CEO says restart expected in 2026, ahead of a March 2027 power-supply contract; prior end-2025 and February 2026 targets were missed and no firm date is set. Fuel (68 assemblies) is on site but not yet loaded as of July 2026.
Details
| Design | Combustion Engineering PWR |
| Capacity | 800 MWe |
Milestone history
- Announced October 2023
- Construction start —
- Fuel load —
- First criticality target 2026
- Grid connection —
- Commercial operation —
References
- NS Energy — Holtec filed NRC restart application October 2023; DOE $1.52B loan
- WNN, Oct 2025 — Palisades receives 68 fuel assemblies after NRC returned plant to operating status (Aug 2025)
- ANS Nuclear Newswire, Jul 8 2026 — major restart projects complete, fuel ready for loading, no firm restart date; CEO expects restart in 2026
- Michigan Public, Dec 2025 — restart pushed to early 2026