goingcritical:pfbrIndia · Power reactor
PFBR (Prototype Fast Breeder Reactor)
Site: Kalpakkam, Tamil Nadu
Status: Critical since April 6, 2026 critical
Summary:
India's first commercial-scale fast breeder reactor and the key step in stage two of its three-stage nuclear programme; criticality came roughly 15 years behind original schedule
Details
| Design | Sodium-cooled prototype fast breeder reactor (MOX fuel) |
| Capacity | 470 MWe |
Milestone history
- Announced —
- Construction start October 2004
- Fuel load October 18, 2025
- First criticality April 6, 2026
- Grid connection —
- Commercial operation —