goingcritical:rooppur-1Bangladesh · Power reactor
Rooppur-1
Site: Rooppur, Ishwardi, Pabna District
Status: Fuel loaded — target criticality 2026 (confidence: medium) target
Summary:
First nuclear power reactor in Bangladesh
Revised schedule agreed June 2025 targets commercial operation December 2026; initial ~300 MW generation expected July-August 2026. Loading of all 163 fuel assemblies completed mid-May 2026.
Details
| Design | VVER-1200/V-523 |
| Capacity | 1080 MWe |
Milestone history
- Announced —
- Construction start November 30, 2017
- Fuel load April 28, 2026
- First criticality target 2026
- Grid connection —
- Commercial operation —