goingcritical:saeul-3South Korea · Power reactor

Saeul-3

Status: Critical since April 12, 2026 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. Operating In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.

Site: Ulju County, Ulsan

North KoreaOsakaBeijingShanghaiTokyoSeoulChangwonZhucheng
Ulju County, Ulsan35.3213° N, 129.2942° E
Summary:

Formerly Shin-Kori 5; operating licence issued December 2025, NSSC cleared initial criticality 10 April 2026 and it was achieved two days later. Commercial operation expected around August 2026.

Details

DesignAPR1400
Electrical output1,340 MWe

Milestone history

  1. Announced
  2. Construction start April 1, 2017
  3. Fuel load
  4. First criticality April 12, 2026
  5. Grid connection
  6. Commercial operation