goingcritical:seabrookUnited States · Power reactor

Seabrook

Status: Operating critical since June 13, 1989 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. Operating In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.

Site: Seabrook, New Hampshire

New YorkTorontoProvidenceColumbusBaltimoreClevelandOttawa
Seabrook, New Hampshire42.8989° N, 70.8508° W
Summary:

One of the newest US reactors; long-delayed by regulatory and financing disputes

Details

DesignWestinghouse 4-loop PWR (Generation II)
Electrical output1,246 MWe

Milestone history

  1. Announced
  2. Construction start July 7, 1976
  3. Fuel load
  4. First criticality June 13, 1989
  5. Grid connection May 29, 1990
  6. Commercial operation August 19, 1990