goingcritical:tsuruga-1Japan · Power reactor
Tsuruga 1
Status: Shut down reached first criticality October 3, 1969 Reactor status full glossary → Announced Publicly announced — a site and design are proposed, but construction has not begun. Site preparation Early site and civil works are under way; the first safety-related ("nuclear") concrete has not yet been poured. Under construction Formal construction has begun, marked by the first nuclear concrete. Fuel loaded Nuclear fuel has been loaded into the core. The reactor is fuelled but has not yet gone critical. Critical Has reached first criticality — a self-sustaining chain reaction, usually at low power — but is not yet connected to the grid. Grid connected Synchronised to the electrical grid and exporting power for the first time, but still in commissioning and power-ascension testing — not yet in commercial service. In commercial operation — the operator has formally declared the unit in regular commercial service. Shut down Permanently shut down and no longer generating; may be defuelled, undergoing decommissioning, or preserved in place. Canceled Abandoned before completion.
Site: Tsuruga, Fukui
Japan's first light-water reactor and one of its earliest commercial units, a GE BWR at the Tsuruga site. Permanently shut down 2015-04-27.
Details
| Design | GE BWR-2 (Mark I containment) |
| Electrical output | 340 MWe |
Milestone history
- Announced —
- Construction start April 22, 1966
- Fuel load —
- First criticality October 3, 1969
- Grid connection November 16, 1969
- Commercial operation March 14, 1970